Eastern Feeder Roads
(1990) in Tashigang area of BHUTAN
- CEMAT in association with Snowy Mountains Engineering Corporation Ltd. of Australia
- Survey, design, cost estimate and preparation of Tender Documents
- 56 km of Eastern Feeder Roads
- The project was undertaken for Government of Bhutan/UNDP.
- The design of the roads were carried using computer aided design method GEOCOM.
- The survey was carried using total stationed type EDM equipments and plotting and design works was carried by CAD method (1990)
Andkhoy – Qaisar Road Project (211.2 km) (Jan. – May 2007), AFGHANISTAN
- Rehabilitate and reconstruct 211.20km of road (black top) from Andkhoy to Qaisar
- Provide road tolling and axle-load control facilities.
- As associate of SMEC (Australia), Emergency Improvement Rehabilitation Project Phase II, TIMOR-LESTE
- As associate of SMEC (Australia) and KWK of Timor-Leste
- Detailed Design and Documentation of Road Improvement in 2004/2005.
- 63.10 Km, Bancau to Viqueque
- 85.20 Km, Manatuto to Naraboro
- 45.00 Km, Tibar to Ermere
- 62.50 Km, Ermere to Malania
- 50.90 Km, Maliana to Zumelai
- 07.00 Km, Bobonaro to Lolotoe
- Project was administered through ADB Grant No. 8198- TF for Ministry of Transport, Communication and Public Works
Design of Water Supply Rehab for Kobe, Fukuzaki, Naga, Numura and Huku Cities of JAPAN
- CEMAT has carried out 9 assignments for Meikan Consultants Co. Ltd. of Japan
- All the design works were carried out in Kathmandu and forwarded to Japan using AutoCAD programme with some training from Meikan Consultants Co. Ltd. In Japan (from 1995 to 2002).
Taluqan – Faisabad Road Rehabilitation Projects, 2003, AFGHANISTAN
- Study of alignment geology and concept designs of landslide protection, debris flows, rock cutting, slope stabilization, rock gallery, snow gallery, cause ways and check dam
- Funded by World Bank
- Services for SMEC International Pty. Ltd
Kabul Urban Road Improvement Project (75 km) (Jul 2008 – Aug 2009), AFGHANISTAN
- Detailed design and construction supervision.
- As associate of SMEC (Australia).
Road Administration Engineering Consultancy Services (Local Project), (Jan. – Feb. 2009), Kuwait
- Preliminary and detailed design of multiple lane road (9 km).
- As associate of SMEC (Australia).
Road Sector Improvement Project 2006, TIMOR-LESTE
- Detailed Design and Documentation
- As associate of SMEC (Australia) and KWK of Timor-Leste
- 09.9 Km Oeleu – Lourba (A12)
- 13.0 Km Lourba – Zumalai (A12), Phase I
- 13.0 Km Lourba – Zumalai (A12), Phase II
- 10.1 Km Aituto – Betulala (A05)
- 19.4 Km Betulala – Same (A05)
- 55.8 Km Viqueque – Uatucarbau (A08)
- 27.0 Km Manatutu – Natarboro (A9)
- Ermera – Bridge options
Dushanbe – Kyrgyz Border RPR Phase one Project (ADB 2062 – TAJ CSF).
(May – July 2005), TAJIKISTAN
The services includes as associate to SMEC (Australia):
- Review detailed design and contract documents for ICB contracts and re-confirm the scope of work.
- Prepare detailed design and LCB bidding documents for the local road improvement component.
- Construction supervision and contract management ensuring execution and quality of rehabilitation work including the rural roads with regard to workmanship and compliance with specifications.
- Supervising and performing tests on materials and/or works and advising on approval or disapproval of the contractor’s plant and equipment.
- Proposing if required, the uncovering of completed rehabilitation or maintenance works and the removal and substitution of inferior materials and/or works.
District Capitals Water Supply Project/ ADB Grant: 0258 – TIM (Nov. 2012 – April 2015), TIMOR-LESTE
- Guidance and Technical direction for design, supervision and oversight of O&M of water supply components;
- Procurement of all goods, materials, supplies, and services (including consultancy and contracting services) in compliance with government procedures and ADB guidelines;
- Financial management;
- Monitoring and evaluation (M&E) of project impacts, outcomes, and outputs;
- Preparation of contracts, bid documents, bidding and evaluation procedures, and contractor selection;
- Update of EMP and preparation of water safety plans, in accordance with ADB guidelines.
Existing Borehole intake in Samoro that will be used for the proposed project.
Existing Water source in Oetulo that will be repaired and used for the proposed Project.
Existing Reservoir tank for Oetulo water source that needs to be repaired and new reservoir and treatment plant to be constructed.
Distribution Pipe line in Pante Macasar. Combination of pipe between GI and Poly for Community or beneficiaries
The Expansion, Rehabilitation and Operation and Maintenance of Pante Macasar Water Supply Systems
Weteen Water Source recommended from Community and stake holder for the proposed project in Manatutu.
Existing Transmission Pipe line from JICA Borehole to Saututun Reservoir tank in Manatutu.
Existing Reservoir Tank in Saututun, Manatuto District, this tank will be used as well for the proposed Project.
Existing Distribution system from reservoir in Saututun to Community in Manatuto District.
The Expansion, Rehabilitation and Operation and Maintenance of Manatuto Water Supply Systems